Bulletin Updates

FC stage-1 was approved by the DFO and stage 2 is pending at the DFO level – Software update: Power projects, 4 Aug 2022

Aug 04, 2022

Rs 60 crore construction of 132 kV S/C on D/C Tower: Conductor package in September

Detailed survey and investigation have been completed and a soil test was completed for lattice tower erection. land acquisitions have been completed for the T/L work.

The application for forest clearance is pending at the nodal office. deer conductor package is likely to be floated in September 2022

Rs 11000 crore greenfield hydroelectric project: HM works package in last quarter of 2022

EC for the project has been approved by the CEA

FC stage-1 was approved by the DFO and stage 2 is pending at the DFO level

WL clearance has been approved by the NBWL

Approach road constructions have been completed.

The civil works contractor has completed the mobilization of equipment at the site.

The HM works package is likely to be floated in Q4 2022.

Rs 4500 crore greenfield hydroelectric pumped storage project: EIA consultants package ahead

TOR was granted by the MoEF.

The capital approval was granted by the state cabinet committee.

Mantec was selected as a consultant for the DPR.

EOI for EIA /EMP consultants is likely to be floated in October 2022.

Rs 900 crore greenfield hydroelectric project: Drilling works package ahead

TOR was granted by the MoEF.

EIA consultant has been selected.

Geotechnical investigation and topographical surveys report are under approval.

Approach road constructions have been completed.

Drilling and drifting works are likely to be floated in September 2022.

Get in touch with us for more on these projects