The FC stages -1 and 2 were granted by the DFO. – Software update: Power projects, 29 Jul 2022
Jul 29, 2022
Rs 200 crore Construction of 400 KV D/C transmission line: Conductor package
The FC stages -1 and 2 were granted by the DFO.
The erection of the lattice tower is in progress and it is in the advanced stage of completion
The detailed engineering was completed at S/S
The ACSR moose conductor package is likely to be floated in August 2022
Rs 5000 crore hydroelectric power greenfield project : Transmission works
The foundation stone of the project has been laid by the Prime Minister of India
The civil works for the construction of HRT works are in progress
The Boring works for TRT are in progress.
Patel Engineering Pvt. Ltd. was involved in the civil works package.
The 400kV S/S works are likely to be floated in September 2022.
Rs 6500 crore super-critical thermal power expansion project (stage-III): FGD works
The PG test was completed for ESP
The erection and installation of pressure parts are in the advanced stage for completion.
The Civil and structural works for the FGD were completed
The absorber system package is likely to be floated in August 2022.
Rs 7000 crore off-Stream closed loop greenfield pumped storage project: EIA/EMP consultant needed
The PFR was prepared by using in-house resources
The soil test at the site was completed.
The application for FC is not yet submitted.
The EOI for EIA consultants is likely to be floated in Q4 2022