Jul 28, 2022
Rs 4500 crore supercritical thermal power brownfield project: Switchyard package ahead
The civil works were completed for BTG and ESP units but structural works are in progress for the same.
AHP package was awarded to M/S MacawberBeekey Pvt. Ltd.
The erection and installation of pressure parts are yet to start for BTG
The Switchyard package is likely to be floated in September 2022.
Rs 350 crore construction of 132 kV D/C on S/C T/L project: P/S works package ahead
The detailed survey and investigation were completed for lattice tower erection
The detailed engineering works were completed for sub-station works.
Private land acquisitions were completed for the lattice tower
The P/S works are likely to be floated in August 2022.
Rs 14000 crore greenfield Hydroelectric project : Civil works package ahead
The forest clearance stage-2 is pending at the nodal office.
The CWC has approved the hydrology report.
The drilling works are completed and drifting works are in progress at the site.
The civil works (lot-2) package is likely to be floated in Q4 2022.
Rs 11030 crore standalone pumped storage project: EM works package RFQ ahead
The forest clearance stage-2 is pending at the DFO
The WL clearance was approved by the wildlife warden
The pre-bid meetings for the EPC package of electro-mechanical works package in August.
The HM works package is likely to be floated in Q4 2022