The Switchyard package is likely to be floated in September 2022. – Software update: Power projects, 28 Jul 2022

Jul 28, 2022

Rs 4500 crore supercritical thermal power brownfield project: Switchyard package ahead

The civil works were completed for BTG and ESP units but structural works are in progress for the same.

AHP package was awarded to M/S MacawberBeekey Pvt. Ltd.

The erection and installation of pressure parts are yet to start for BTG

The Switchyard package is likely to be floated in September 2022.

Rs 350 crore construction of 132 kV D/C on S/C T/L project: P/S works package ahead

The detailed survey and investigation were completed for lattice tower erection

The detailed engineering works were completed for sub-station works.

Private land acquisitions were completed for the lattice tower

The P/S works are likely to be floated in August 2022.

Rs 14000 crore greenfield Hydroelectric project : Civil works package ahead

The forest clearance stage-2 is pending at the nodal office.

The CWC has approved the hydrology report.

The drilling works are completed and drifting works are in progress at the site.

The civil works (lot-2) package is likely to be floated in Q4 2022.

Rs 11030 crore standalone pumped storage project: EM works package RFQ ahead

The forest clearance stage-2 is pending at the DFO

The WL clearance was approved by the wildlife warden

The pre-bid meetings for the EPC package of electro-mechanical works package in August.

The HM works package is likely to be floated in Q4 2022