Bulletin Updates

The limestone and gypsum handling system package is likely to floated in August 2022| – Software update: Power projects, 27 Jul 2022

Jul 27, 2022

Rs 11000 thermal power expansion project: FGD works ahead

The BOP works are in progress and are in the advanced stage of completion.

Mechanical completion for BTG is yet take place

The Civil works for the Railway siding package were completed and structural works are in initial phase.

The limestone and gypsum handling system package is likely to floated in August 2022|

Rs 320 crore construction of 132 Kv S/C on D/C transmission line : P/S Works package ahead

The private land acquisitions were completed for the T/L works.

Application scivil aviation, defense, and PTCC submitted and are under process for approval..

The private land acquisition was completed for the substation and detailed engineering works were completed.

Rs 6000 greenfield multipurpose project : Civil works RFQ ahead

The hydrological report was approved by the Ministry of Water Resources

The public hearing was completed

The Forest clearance stage-2 was accorded by DFO for the diversion of forest land.

The civil works package(Lot-2) is likely to be floated in September 2022.

Rs 5468.30 greenfield integrated renewable energy pumped storage project: Transmission works ahead

The Civil and HM packages were awarded.

ANDRITZ was selected as an EM contractor.

The contractor has started the mobilization of equipment at the site.

The EPC package for the transmission line is likely to be floated in Q4 2022.

Get in touch with us for more on these projects

The full story is for subscribers. Log in to read it, or start a free trial.
Log in Start a free trial »