Rs 11000 thermal power expansion project: FGD works ahead
The BOP works are in progress and are in the advanced stage of completion.
Mechanical completion for BTG is yet take place
The Civil works for the Railway siding package were completed and structural works are in initial phase.
The limestone and gypsum handling system package is likely to floated in August 2022|
Rs 320 crore construction of 132 Kv S/C on D/C transmission line : P/S Works package ahead
The private land acquisitions were completed for the T/L works.
Application scivil aviation, defense, and PTCC submitted and are under process for approval..
The private land acquisition was completed for the substation and detailed engineering works were completed.
Rs 6000 greenfield multipurpose project : Civil works RFQ ahead
The hydrological report was approved by the Ministry of Water Resources
The public hearing was completed
The Forest clearance stage-2 was accorded by DFO for the diversion of forest land.
The civil works package(Lot-2) is likely to be floated in September 2022.
Rs 5468.30 greenfield integrated renewable energy pumped storage project: Transmission works ahead
The Civil and HM packages were awarded.
ANDRITZ was selected as an EM contractor.
The contractor has started the mobilization of equipment at the site.
The EPC package for the transmission line is likely to be floated in Q4 2022.