Rs 2500 crore greenfield hydroelectric project: EM package ahead

The EC and forest clearance stage -1 was accorded by the MoEF and CC

LOA for the civil and HM works is expected by Aug. 2022

Find out who the major contractors involved in the project are

The EM package is likely to be floated in September 2022

Rs 1100 crore greenfield hydroelectric project: EPC package ahead

The civil works contractor has started work

The HM works contractor has completed the mobilization.

Find out who the major contractors are.

The EPC package for power evacuation is likely to be floated in Q4 2022

Rs 700 crore greenfield hydroelectric project: Civil works

The hydrology report was accorded by the CWC.

WAPCOS completed the [re[aration of New DPR.

Pre-bid meetings for the civil works package(lot-1) are about to conduct.

Civil works package(lot-2) is likely to be floated in October 2022

Khetri-Narela Transmission Ltd seeks transmission licence

The company are seeking transmission licence to establish “Transmission System Strengthening Scheme for Evacuation of Power from SEZ in Rajasthan (8.1 GW) under Phase-II Part-G”

Find out what the regulator said

Rs 950 crore greenfield hydroelectric project: PMC selected, civil works package ahead

SIA report is at an advanced stage of completion

Construction of the approach road to the dam site has been completed.

PMC has been selected

DPR is at an advanced stage for completion.

Civil works package is expected by Q4 2022.

Rs 500 crore greenfield hydroelectric project: EPC package ahead

Social impact assessment studies have been conducted by AFC India Ltd

The public hearing was completed.

The state govt has completed the construction of the approach roads

EPC package for main plant works is likely to be floated in October 2022.

Rs 400 crore thermal power station renovation and modernization project: TG retender soon

The tender for the SG package was floated.

Find out who are the qualified bidders under techno-commercial bidding.

Retender soon for the TG.

RMLE works for DeNOx and ESP is likely to be floated in August 2022.

Rs 200 crore 220 KV D/C transmission line: Package ahead

The survey and investigation for the same were completed.

FC stage -2 has been granted in January

Moose conductor package is likely to be floated in August 2022.