Jul 20, 2022
Ammonia-Urea Greenfield Project
Cost: 5500 Cr.
Project Event: The project is still on hold due to lack of funds, The company wants to complete a few small projects first, which is ongoing inside the plant. The project is likely to be active in Q3 FY 2022-2023
Urea (Granular) and Captive Power Unit Expansion Project
Cost: 700 Cr.
Project Event: The project is still on hold, It is likely to be activated in Q2 FY 2022-2023. The internal discussion is ongoing; RFQ for the LSTK contractor, which is likely to be released in October 2022