Jul 15, 2022
Rs 6000 crore super-critical thermal power brownfield project (stage-II): BOP works ahead
Pilling and foundation worksare in progress for the ESP package
Contractor details in pre-bid meeting for the PT plant are available.
DM plant package will likely be floated in August 2022.
Rs 1000 crore stage-II hydroelectric greenfield project: Find out who are in the race
Techno-commercial bids were completed for civil works (lot-1)
Find out who are the qualified bidders in the technical bid.
Civil works package(lot-2) will likely be floated in September 2022.
Rs 808.62 crore hydroelectric greenfield project : RFQ Ahead
DPRwas approved by the CEA.
Forest clearance stage 2 is pending at the regional office
The pre-bid meetings for the EPC package for civil and HM works are about to conducted
Rs 350 crore Construction of 400 kV DC transmission line: Moose conductor package ahead
The approval from the NOC from the Inland Waterway Authority of India is pending
Detailed engineering was completed for the 220/132kV substation
The ACSR moose conductor package will likely be floated in August 2022.