Bulletin Updates

PMC package is likely to be floated in September 2022. – Software update: Power projects, 14 Jul 2022

Jul 14, 2022

Rs 550 Crores greenfield hydroelectric power project, stage-II

WAPCOS has prepared the pre-feasibility report.

The hydrology report was completed and it was approved by CWC

PMC package is likely to be floated in September 2022.

Rs 1000 crore greenfield hydroelectric power project: HM package in October

EIA report and the SIA report were completed and it was approved by the MoEF&CC

The validity of EC has just got extended by the MoEF&CC

The HM works package is likely to be floated in October 2022.

Rs 20000 crore greenfield hydroelectric power project: RFQs ahead

The supply of boilers and power cycle piping package is by BHEL

Erection and installation of BTG of unit-1 have been completed

Limestone and gypsum handling plant package is likely to be floated in August 2022.