Bulletin Updates

Project Event: 40 % of construction work has been completed, The commissioning is likely to… – Software update: Fertilizer projects, 13 Jul 2022

Jul 13, 2022

Effluent Treatment Plant Up-gradation Project

Cost: Rs 101 Cr.

Project Event: 40 % of construction work has been completed, The commissioning is likely to be done in January 2023 in place of Nov 2022, due to delay in the construction. All the procurement work has been completed and all the long lead items is been reached the site. Ion-exchange India Ltd is the LSTK contractor.

SSP/GSSP Greenfield Project

Cost: Rs 15 Cr.

Project Event: The proposal for the environmental clearance is likely to be submitted in August 2022, RFQ for the local contractor is likely to be released in August 2022, The company is talking with a different local contractor