RFQ for the S/S works package is likely to be floated in August 2022 – Software update: Power projects, 13 Jul 2022
Jul 13, 2022
Rs 550 crore construction of 400kV QMDC transmission line: RFQ Ahead
Forest clearance for the same is pending at the regional office.
RFQ for the S/S works package is likely to be floated in August 2022
Rs 6000 crore greenfield hydroelectric power project : Civil works coming up
Forest clearance stage-2 is the main hurdle for the execution of the project.
AHP Pre-bid meetings are yet to conduct for Civil works(lot-1)
RFQ for the civil works (Lot -2) is likely to be floated in September 2022.
Rs 5000 crore super-critical thermal power brownfield project : CW system package
Civil, structural, and architectural works at the BTG site are in progress
AHP plant will be modernized and dismantling works were completed
CW system package is likely to be floated in September 2022.