Project Event: The Pilot Plan is still in progress at the Company’s R&D department, It is… – Software update: Fertilizer projects, 7 Jul 2022
Jul 07, 2022
NPK Pilot Plant Greenfield Project
Cost: 700 Cr.
Project Event: The Pilot Plan is still in progress at the Company’s R&D department, It is likely to be completed in at the end of September 2023, Based on inputs from the R&D department, the development of a pilot plant shall be taken up. RFQ for the equipment and services is likely to be completed in October 2022.
Sulphuric Acid Greenfield Project
Cost: 50 Cr.
Project Event: RFQ for the local contractor & services is likely to be released in August in place of July 2022, due to delay in the internal discussion. The project has elicited the environmental clearance in March 2022