Wagon Tippler works package is likely to be floated in Q3 2022. – Software update: Power projects, 17 Jun 2022

Jun 17, 2022

Rs 10000 Crore ultra-super-critical thermal power project, stage-III

Civil works are in progress for BTG works

Pilling and foundation are in progress BOP works

Wagon Tippler works package is likely to be floated in Q3 2022.

Rs 1300 crore greenfield hydroelectric power project

Modifications in DPR are in progress

Re-assessment of hydrology report is in progress.

EPC package for civil works package is expected soon.

Rs 442.31 crore greenfield hydroelectric power project

Stage-2 clearance is pending at the DFO.

RFQ for the PMC package is likely to be floated in July 2022.