Jun 15, 2022
Rs 4500 crore greenfield hydroelectric power project
Mobilization of equipment is in progress at the site.
FC stage-2 is pending at DFO.
RFQ for the HM works package is expected soon.
Rs 8500 crore greenfield hydroelectric power project
S/S tender floated and pre-bid meetings are yet to be conducted.
Erection and installation of TG units are in progress.
RFQ for the 250 KVA P/S works is expected.
Reconductoring of MePTCL lines: Business opportunities
Meghalaya Power Transmission Corporation Ltd (MePTCL) plans to reconductor the existing 132 KV single circuit line with HTLS conductor
There are business opportunities ahead
Old hydel power plant: Business opportunities
This hydel power plant is going to complete 25 years of service
The owner plans a replacement of old equipment
More business opportunities ahead
Rs 2000 crore greenfield hydroelectric power project
Pilling and foundation works were completed.
FC stage-2 is pending at DFO. Detailed engineering works are in progress for P/S works.
RFQ for the ACSR moose conductor package is likely to be floated in July 2022.
Rs 2000 crore greenfield hydroelectric power project
PPA was signed with the government.
880% of the total land acquisition was completed.
EPC package for civil and HM package is expected.
Rs 323 crore 400 kV SC line to DC line with QUAD Moose ACSR
Detailed engineering was completed for S/S.
Forest clearance stage is yet to be granted.
EPC package for T/L works is likely to be floated in Q3 2022.