Project Event: PDIL has been selected for the preparation of the Techno-Economic Feasibility… – Software update: Fertilizer projects, 14 Jun 2022
Jun 14, 2022
DAP/NPK Greenfield Project
Cost: 300 Cr.
Project Event: PDIL has been selected for the preparation of the Techno-Economic Feasibility Report. Based on the feasibility report of PDIL, future action shall be planned. The Feasibility study is still ongoing, which is likely to be completed in Q2 FY 2022-2023. RFQ for the LSTK contractor is likely to be released in Q2 FY 2022-2023.
Ammonia Storage Tank Greenfield Project
Cost: 100 Cr.
Project Event: RFQ for the ammonia storage tank with associated facilities has been re-released, and for which bid due date has been extended from 9 June to 8 July 2022 due to lack of bidder. In the previous RFQ, Vijay Tank Was in the race