EPC package for T/L works is likely to be floated in Q3 2022. – Software update: Power projects, 14 Jun 2022

Jun 14, 2022

Rs 323 crore 400 kV SC line to DC line with QUAD Moose ACSR

Detailed engineering was completed for S/S.

Forest clearance stage is yet to be granted.

EPC package for T/L works is likely to be floated in Q3 2022.

Rs 2000 crore greenfield hydroelectric power project

PPA was signed with the government.

880% of the total land acquisition was completed.

EPC package for civil and HM package is expected.

Rs 12000 crore brownfield super-critical thermal power project

BOP works are in the active phase of construction.

Construction works were delayed due to the slow progress of sub-contractors detailed design and engineering.

RFQ for the absorber system package is likely to be floated in Q3 2022.

Rs 3000 crore greenfield hydroelectric project : RFQ Ahead

EIA/EMP study is in progress and it is in an advanced stage for completion.

Preparation of DPR was completed and it was approved.

PMC package is likely to be floated in August 2022