Forest clearence stage-2 is pending at DFO – Software update: Power projects, 13 Jun 2022
Jun 13, 2022
Rs 6922 crore greenfield pumped storage project: Civil works package ahead
DPR is in an advanced stage of approval
Forest clearence stage-2 is pending at DFO
PMC package awarded for the same project
Civil work package(Lot-1) is likely to be floated by Q3 2022
Rs 2990 crore greenfield pumped storage project :Transmission package ahead
EM package contractor has mobilized the equipment at the site.
HRT works are in the advanced stage for completion.
EPC RFQ for power evacuation packages is likely to be floated in August 2022.
Rs 2990 crore greenfield hydroelectric power project : PMC Package in Q-3, 2022
Wildlife clearance (WC) is in progress
Geotechnical investigation and topographical survey were completed
PMC package is likely to be floated in the second half of Q3 2022.
Rs 730 crore construction of 220 kV S/C transmission line: RFQ ahead
Detailed engineering works are in progress at the P/S site
Erection and fabrication works are in progress at the GIS substations.
ACSR Deer conductor package is likely to be floated
(Get in touch with us if you want to know more about these projects)