Energy Saving-cum- Ammonia-Urea Expansion Project
Cost: 540 Cr.
Project Event: Critical equipment purchase has been completed, all the equipment have reached the site, 90 % of construction work has been completed the installation of long-lead items is ongoing. The pre-commissioning is continuing, the project is likely to be commissioned at the end of July 2022 in place of June 2022.
SSP Expansion Project
Cost:21 Cr.
Project Event: The project is under environmental clearance. It is likely to be elicited in July 2022. The RFQ for the local contractor is likely to be released after environmental clearance