RFQ for the 400 kV P/S package is likely to be floated in July 2022. – Software update: Power projects, 8 Jun 2022
Jun 08, 2022
Rs 653 crore Construction of 400 kV transmission line: RFQ ahead
Detailed engineering completed at the substation sites.
RFQ for the 400 kV P/S package is likely to be floated in July 2022.
Rs 10000 crore thermal power project: NDTC package ahead
Work stopped due to agitation by the farmers and issues connected with the National Green Tribunal
Consultants has submitted the feasibility and viability of the newly allocated land.
RFQ for the NDCT package is likely to be floated soon.
Rs 3000 crore pump storage project: When is drilling work package to be expected?
Land acquisition is in progress
Find out who are the DPR and EIA consultants in the same project.
RFQ for the drilling works package is expected.
Rs: 3500 crore pump storage project: Civil work (Lot-1 package) likely in Q3, 2022
Forest clearance stage-2 is pending at DFO.
DPR in advanced stage for completion
RFQ for the civil works package(lot-1) is likely to float in Q3 2022.
Get in touch with us for more on these massive power sector projects