Ammonia-Urea Brownfield Project

Cost: 6000 Cr.

Project Event: The RFQ for the Cooling Tower as well as Cooling Water Treatment Package has been out and bid due date is 6 June 2022. The bid due date has been extended from 17 May to 30 May 2022 for the Supply, Installation & Testing of the Flare System. The Tender for Instrument Air & Plant Air System has been canceled due to higher price quoted by the L1 bidder than the estimated cost, The L1 bidder was Linde. BTL EPC, Macawber Beekay & Tata Project are in the race for the supply of Urea handling & baggage packages on an LSTK basis, The technical bid opening is in progress.

Ammonia-Urea Brownfield Project

Cost: 6500 Cr.

Project Event: RFQ for the sheeting cladding in wagon loading platform has been out and bid due date is 3 June 2022. 96 % of construction work has been completed, and the equipment installation is ongoing. Procurement of machinery orders are already completed, procurement of other services is ongoing, also pre-commissioning is ongoing, Commercial production is likely to be started from September in place of June 2022, due to delay in the construction.

The full story is for subscribers. Log in to read it, or start a free trial.
Log in Start a free trial »