Project Event: The proposal for the environmental clearance is likely to be submitted in Q2… – Software update: Fertilizer project, 23 May 2022
May 23, 2022
Ammonia Greenfield Project
Cost: 2773 Cr.
Project Event: The proposal for the environmental clearance is likely to be submitted in Q2 FY 2022-2023. The RFQ for the contractor is likely to be released in Q2 FY 2022-2023.
Ammonia-Urea Energy Saving Project
Cost: 380 Cr.
Project Event: The PDP development is still ongoing and expected to be received by the end of July 2022, RFQ for the LSTK contractor is likely to be re-released in July 2022. Accordingly, the services of M/s CASALE had been engaged to carry out the Process Design Package (PDP) for the ESP schemes and their integration. However, due to financial liquidity issues faced by the Company, the PDP development had not proceeded as envisaged but was resumed through the commencement of the Kick-off Meeting in December-2020