Customize Blending Unit for NPK Fertilizer & Ammonia Storage Tank Greenfield Project
Cost:90 Cr.
Project Event: The project is on hold due to the financial loss during Covid, and it is likely to be activated in Q2 FY 2022-2023. RFQ for the Contractor is likely to be released in Q2 FY 2022-2023.
Single Super Phosphate Expansion Project
Cost:20 Cr.
Project Event: The Details Engineering is ongoing, construction is likely to be started in August 2022, the company has its own engineering team. The commissioning is likely to be completed in December 2023