Project Event: The procurement of long-lead items by Toyo Engineering is ongoing.… – Software update: Fertilizer projects, 26 Apr 2022
Apr 26, 2022
Ammonia Storage Tank Greenfield Project
Cost: 88 Cr.
Project Event: The procurement of long-lead items by Toyo Engineering is ongoing. Construction is likely to be started at the end of May 2022 due to a delay in the purchase. Toyo was the single bidder for the 10000 MT double-wall supply with associated facilities on an EPCC- LSTK basis. The project is likely to be commissioned in Q2 FY 2023-2024.
NPK Pilot Plant Greenfield Project
Cost:90 Cr.
Project Event: The Pilot Plan is still in the progress at the Company’s R&D department, Which is likely to be completed in Q2 FY 2022-2023, Based on inputs from the R&D department, the development of a pilot plant shall be taken up. RFQ for the equipment and services is likely to be completed in Q2 FY 2022-2023