SSP/NPK Greenfield Project
Cost: 70 Crore
Project Event: Still, the feasibility studies are ongoing, It is likely to be completed in May 2022. The company is planning to submit the proposal for the environmental clearance in Q1 FY 2022-2023. due to the delay in the feasibility study. RFQ for the contractor is likely to be released after the clearance