Effluent Treatment Plant Up-gradation Project

Cost: 101 Cr.

Project Event: All the procurement work has been completed and all the long lead items have reached the site. Ion-exchange India Ltd is the LSTK contractor. The construction is likely to be started at the end of Feb 2022 in place of December 2021, due to Covid.

Sulphuric Acid Greenfield Project

Cost: 50 Cr.

Project Event: The review is still ongoing in the MoEF, clearance is likely to be elicited in February 2022, RFQ for the local contractor as well as equipment supplier is likely to be released in March 2022