Dec 21, 2021

Energy Saving-cum- Ammonia-Urea Expansion Project

Cost: 540 Cr.

Project Event: Critical equipment purchase has been completed, all equipment have been reached the site, 60 % of construction work has been completed, the installation of long-lead items is ongoing. The project is likely to be commissioned in June 2022.

NPK Plant Greenfield Project

Cost: 915 Cr.

Project Event: The proposal has been accepted by DOF, RFQ for the environmental consultant is likely to be released in January 2022