Project Event: Toyo engineering is the single bidder for the 10000 MT double-wall supply with… – Software update: Fertilizer projects, 29 Nov 2021
Nov 29, 2021
SSP-Sulphuric Acid & NPK Fertilizer Expansion Project
Cost: 75 Cr.
Project Event: The environmental clearance has been elicited in September 2019. Concern to establish has been approved. RFQ for the local contractor is likely to be released in January 2022.
Ammonia Storage Tank Greenfield Project
Cost: 100 Cr.
Project Event: Toyo engineering is the single bidder for the 10000 MT double-wall supply with associated facilities on an LSTK basis. The purchase of equipment and services is still ongoing, construction is likely to start at the end of December 2021 whereas it was meant to start earlier in October, 2021.