Project Event: The project is still on hold due to a lack of funds, and it is likely to be… – Software update: Fertilizer projects, 9 Nov 2021
Nov 09, 2021
Ammonia-Urea Energy Saving Project
Cost:380 Cr.
Project Event: The project is still on hold due to a lack of funds, and it is likely to be activated in January 2022. RFQ for the LSTK contractor is likely to be re-release in March 2022
NPK Fertilizer Greenfield Project
Cost: 1517 Cr.
Project Event: Project activities are still on hold, internal discussion is ongoing between the JV for the hiring of the LSTK contractor, RFQ for the LSTK contractor is likely to be re-released in February 2022.