Software update: Fertilizer projects: Cost-150 Cr, Cost: 9 Cr. – 1 Nov 2021
Nov 01, 2021
Ammonia-Urea Expansion Project
Cost-150 Cr
Update: The project has elicited environmental clearance in Jan 2020, but due to a lack of funds it is on hold, the company has applied for a loan, sanction is likely to be elicited in December 2021. RFQ for the EPC contractor is likely to be released in January 2022.
Ammonium Sulphate Expansion Project
Cost: 9 Cr.
Update: The company will execute the project on its own, without involving any external technology supplier and it shall be using its available in-house expertise and resources. The public hearing has been completed, the proposal for the environmental clearance is likely to be granted in November 2021. RFQ for the EPC contractor is likely to be released in January 2022