Bulletin Updates

Project Event: Studies are still ongoing, the proposal for the environmental clearance is… – Software update: Fertilizer projects, 9 Sep 2021

Sep 09, 2021

NPK Pilot Plant Greenfield Project8Cost - Rs 90 crore

Project Event: The Pilot Plan is in progress at the Company's R&D department. Based on inputs from the R&D department, the development of a pilot plant shall be taken up.

Single/Triple Super Phosphate Greenfield Project8Cost - Rs 25 crore

Project Event: Studies are still ongoing, the proposal for the environmental clearance is likely to be submitted in October 2021. RFQ for the local contractor is likely to be released in November 2021