Project Event: Bid due date for the Urea handling & bagging package is 5 October 2021 – Software update: Fertilizer projects, 23 Aug 2021

Aug 23, 2021

Effluent Treatment Plant Up-gradation Project8Cost - Rs 101 crore

The LSTK contractor is still continuing with equipment purchases

Ammonia-Urea Energy Saving Project8Cost - Rs 250 crore

Project Event: The feasibility studies are still ongoing, and are likely to be completed in September 2021, RFQ for the LSTK contractor is likely in Q3 FY 2021

Ammonia-Urea Brownfield Project8Cost - Rs 6000 crore

Project Event: Bid due date for the Urea handling & bagging package is 5 October 2021

Ammonium Nitrate Melt Greenfield Project8Cost - Rs 88 crore

Project Event: The Letter of bid invitation for the LSTK contractor has come out and the bid due date has been extended from 6 August to 27 August 2021