ONGC's $ 5 billion KG-DWN-98/2: Slack work? – 17 Aug 2021
Aug 17, 2021
There is concern in ONGC over the delay in gas production from the KG-DWN-98/2 block.
What are the new milestones for gas production?
Also, the executive director in charge of the block has changed, instead of the hands-on style of the former ED Arvind J Morbale the style of the present incumbent Adesh Kumar is different, often brass. That is slowing things down too, it is reliably learned