Project Event: All the project activities are on hold due to lack of funds, Capital approval… – Software update: Fertilizer projects, 13 Aug 2021
Aug 13, 2021
Ammonia-Urea Energy Saving Project8Cost - Rs 250 crore
Project Event: All the project activities are on hold due to lack of funds, Capital approval is still under process. It is likely to be elicited in Q3FY2021. RFQ for the LSTK contractor is likely to be released in Q3FY2021
SSP Expansion Project8Cost - Rs 21 crore
Project Event: The project is under environmental clearance. Public hearing is likely to be completed at the end of August 2021. The RFQ for the local contractor is likely to be released after environmental clearance, which is likely to be elicited in October 2021.