Project Event: The Pre-Qualification for the LSTK contractor has been out and the discussion… – Software update: Fertilizer projects, 23 Jul 2021

Jul 23, 2021

Urea Revamp Project8Cost - Rs 700 crore

Project Event: The Pre-Qualification for the LSTK contractor has been out and the discussion is still ongoing, It is likely to be finalized in August 2021 in place of June 2021.

SSP/NPK Greenfield Project8Cost - Rs 70 crore

Project Event: Still, the feasibility studies are ongoing, The company is planning to submit the proposal for the environmental clearance in September in place of June 2021 due to the second wave of Covid. RFQ for the contractor is likely to be released after the clearance.