Urea plant: 2.4 mmscmd of gas needed by December – 13 Jul 2021

Jul 13, 2021

Ammonia-Urea Brownfield Project8Cost - Rs 6000 crore

Project Event: 90 % of construction work has been completed, the installation of equipment is ongoing. procurement of machinery orders are already completed, procurement of other services is ongoing, commissioning is likely to be in Dec 2021. Earlier the commissioning date was October.

However this date may slip, according to our own estimation.