Project Event: The procurement work is ongoing. The construction has been started in February… – Software update: Fertilizer projects, 30 Jun 2021
Jun 30, 2021
Phosphoric Acid Expansion Project8Cost - Rs 1100 crore
Project Event: The procurement work is ongoing. The construction has been started in February 2020. Now the construction is ongoing on full fledge, Labour and other services are available as per requirement. 68 % of civil work has been completed, the erection of different equipment is ongoing. The Company has been selected Jacob as the EPCM contractor, The commissioning has been extended from March 2021 to October 2021.
Ammonia/Nitric Acid/SOP Greenfield Project8Cost - Rs 200 crore
Project Event: The proposal for the term of reference has been granted, and the final EIA report preparation is still ongoing, the proposal for environmental clearance is likely to be submitted at the end of July 2021. RFQ for the local contractor is likely to be released in August 2021.