Project Event: Still, evaluation is ongoing for environmental clearance, and it is likely to… – Software update: Fertilizer project, 2 Jun 2021
Jun 02, 2021
Single Super Phosphate Greenfield Project 8Cost - Rs 10 crore
Project Event: Still, evaluation is ongoing for environmental clearance, and it is likely to be granted in June 2021. A new project committee has been formed for the project within the country, and the tender for a contractor is likely to be released in July 2021 in place of May 2021.