Bulletin Updates
Process Air Compressor Greenfield Project8Cost - Rs 347 crore – Software update: Fertilizer projects, 31 May 2021
May 31, 2021
Process Air Compressor Greenfield Project
8Cost - Rs 347 crore
Find out when the RFQ will be re-released
DAP Expansion Project
8Cost - Rs 20 crore
The final EIA report has been made, and a proposal for the environmental clearance has been submitted, all, the project activities are likely to be started after the clearance, It is likely to be elicited in June 2021. RFQ for the local contractor is likely to be released in August 2021.
Log in Start a free trial »