DAP Expansion Project
Cost - Rs 442 crore
Project Event: 90 % of construction work has been completed, all the equipment has reached the site, and installation is ongoing. The project is likely to be commissioned at the end of April 2021
Ammonia and Captive Power Unit Greenfield Project
Cost - Rs 1920 crore
Project Event: The project has been elicited the terms of references, The final EIA report preparation is likely to be completed in, April 2021. The proposal for the environmental clearance is likely to be submitted in May 2021. RFO for the EPC contractor is likely to be released in July 2021.