Bulletin Updates

Project Event: The project is still awaiting environmental clearance, the review is ongoing… – Software update: Fertilizer projects, 24 Feb 2021

Feb 24, 2021

Sulphuric Acid and Captive Power Unit Expansion Project 8Cost - Rs 300 crore

Project Event: The project is still awaiting environmental clearance, the review is ongoing, the project is likely to elicit the environment clearance in March 2021, RFQ for the PMC contractor is likely to be released in April 2021

GSSP/GBSSP/GZSSP/GPG/BSP/BSG Expansion Project 8Cost - Rs 48 crore

Project Event: The proposal for the term of references has been granted, the final EIA report preparation is still ongoing. Proposal for environmental clearance is likely to be submitted in March 2021. RFQ for the EPC contractor is likely to be released in April 2021