Rs 6000 crore ammonia-urea plant: Pre-commissioning ongoing, likely to go on stream in February/March – 18 Jan 2021
Jan 18, 2021
Ammonia-Urea Revamp Project
Cost - Rs 6000 crore
Project Event: 99.80 % of the construction work has been completed, and the railway siding has been completed. Pre-commissioning is still ongoing, The commissioning is likely to be completed in February 2021. the schedule of commissioning was 31 March 2020. but due sudden lockdown of the country, authorities stopped all the pre-commissioning activities following the declaration of the holiday for employees, including outsourcing staff. The pre-commissioning works such as target plate flushing for turbine lines, Co2 section commissioning activities, and urea plant water flushing were stalled following the lockdown.