Bulletin Updates

Bio-refinery-II: The promoter says it is still on track but delayed – 18 Jan 2021

Jan 18, 2021

Promoters of this particular bio-refinery is still wanting to go ahead. But work has got delayed as was the case with other 2G refineries

Project Cost: 838 crores

Project Description: The owner along with PMC contractor Engineers India Limited (EIL) is planning to construct an ethanol plant to produce 60 KL fuel-grade ethanol per day, primarily from biomass, and will use approximately 1.5 Lakh tons of biomass per year at Davanagere, Karnataka. PFR report was prepared by Engineers India Limited (EIL). EIA report was prepared by ABC Techno Labs India Pvt. Ltd. but the Environment Clearance (EC) has not been elicited yet.

Event:: RFQ for licensor is expected in March-2021.

The full story is for subscribers. Log in to read it, or start a free trial.
Log in Start a free trial »