News & Bulletin Updates

Aluminum bar prices have moved down in Mumbai.

Read more

Rs 450 crore construction of 765 kV D/C tower: P/S works in September 2022
8The pilling and foundation works were completed.
8EPC selected for S/S works.
8Private land acquisition was completed for S/S.
8P/S works package is likely to be floated in September 2022.
Rs 4000 crore greenfield standalone pumped storage project : EM works in Q4 2022

8The PPA was signed with the owner
8Private land acquisitions and public hearings were completed.
8Forest clearance stage 2 is under process at the regional office
8The pre-bid meetings are about to conduct for the EPC package for civil and hydro-mechanical works.
8The EM works package is likely to be floated in Q4 2022.
Rs 400 crore greenfield hydroelectric project: civil works package(lot-1) in Q4 2022.

8The state PWD department has completed the approach road construction.
8Drilling works at the site were completed and drifting works are in progress.
8Hydrology report has been approved by CWC
8Forest clearance stage 1 was granted by the DFO and stage 2 is in progress at the nodal office.
8The civil works package(lot-1) is likely to be floated in Q4 2022.
Rs 4800 crore thermal power station replacement project: BOP works in October 2022

8EPC has retained its terminated contracts as the verdict comes in favor of them.
8Civil and structural works are in progress at the BTG site.
8Civil and structural works for BOP are in progress
8Sub-contractors selected for DM plant works.
8
PT plant package is likely to be floated in October 2022.
Get in touch with us for more on these projects

Read more

8The case for using LNG in India is crumbling
8Here is an interesting insight

Read more

8Here is are services needed for offshore blocks in the private sector

Read more

What is the quantum of gas sold by HOEC out of its offshore block?
8Also, what is the status of the oil well in the same block?

Read more

8Here is ONGC pushing a drilling programme for an OALP block

Read more

Ammonia-Urea Brownfield Project
8Cost: 6500 Cr.
8Project Event: RFQ for the additional Dryer unit has been out and bid due date is extended from 29 June to 25 August. Comt Construction Private Limited is the L1 bidder for the Sheeting Cladding in Wagon Loading Platform with a price bid INR 2,99,62, 250. Around 96 % of construction work has been completed, and the equipment installation is ongoing. Pre-commissioning is ongoing, Commercial production is likely to be started from September in place of June 2022, due to delay in the construction.
Ammonia-V Revamp Project
8Cost: 102 Cr.
8Project Event: RFQ for the Hot Water & Chilled water package has been out and due date is 23 August 2022. The project is likely to be commissioned in December 2022 in place of October 2022 due to the impact of Covid

Read more

8Project Name: Cuttack District City Gas Distribution
8Project Cost: Rs 350 crore

Read more

8Project Name: Bhubaneswar- Khordha District City Gas Distribution
8Project Cost: Rs 350 crore

Read more

8Project Name: Bhubaneswar- Khordha District City Gas Distribution
8Project Cost: Rs 350 crore

Read more

Petrochem sources reported a significant fall in DEG prices in the Hazira market.

Read more

Butyl carbitol prices were quoted lower in the Kandla chemical market today.

Read more

Isobutanol prices were assessed lower in the Kandla market today.

Read more

Petrochem sources reported a significant fall in ethylene dichloride prices in the Kandla chemical market.

Read more

An elevated trend is noticed in aniline prices.

Read more

Butyl acrylate prices in the Kandla market registered a fall today.

Read more

Petrochem sources reported a rise in PBR grade 1220 prices in the Delhi market today.

Read more

Silver prices witnessed a significant fall in the Ahmedabad market today.

Read more

Phosphorus trichloride prices in the Delhi market have fallen sharply.

Read more

VAM prices were quoted lower in the Hazira chemical market today.

Read more

Propylene glycol prices have witnessed a huge fall in the Kandla market.

Read more

Formaldehyde prices in the Chennai market registered a fall today.

Read more

On August 17, 2022, C9 solvent prices were pushed massively higher in the Kolkata market.

Read more

Petrochem sources confirmed that styrene monomer prices have slipped in the Chennai market.

Read more

8EN24 is medium-carbon low-alloy steel that is commonly used in the production of automotive and machine tool parts

Read more
« First  « 2162 21632164 2165 2166 »  Last
Showing 54075 - 54100 of 94953 Bulletin